On 24th march 2011 we tested conveyor and agitator by changing the contacts manually means without command from slave PLC. Steps are given below for our existing plant:
1.We traced out the proper wiring ,which MCB(Miniature circuit Breaker) is connected through contactor circuit .Wiring diagram will be soon displyed.
2. 3 cables from the motor are connected to contactor n contactor also got connected to cables from R2 ralay and NO ,NC contacts are 11 & 14 in our panel..
3.contactor has supply from the source through MCB.when operator gives command,command from realys comes to contactor and contacts cganged means star to delta & supply get connected to motor/agitator.This is the logic behind wiring diagram
4.This will more understand when we will disply the wiring diagram of our panel.
conveyor motor was 3 phase,so we have to check safety aspects while working in plants.
1.We traced out the proper wiring ,which MCB(Miniature circuit Breaker) is connected through contactor circuit .Wiring diagram will be soon displyed.
2. 3 cables from the motor are connected to contactor n contactor also got connected to cables from R2 ralay and NO ,NC contacts are 11 & 14 in our panel..
3.contactor has supply from the source through MCB.when operator gives command,command from realys comes to contactor and contacts cganged means star to delta & supply get connected to motor/agitator.This is the logic behind wiring diagram
4.This will more understand when we will disply the wiring diagram of our panel.
conveyor motor was 3 phase,so we have to check safety aspects while working in plants.